A Texas AI Campus Clears the Power Hurdle and Waits on a Lease

Power has become the hardest thing to buy in the race to build data centers for artificial intelligence. Land can be found and buildings designed, but steady electricity at the scale these facilities need can take years to secure. That context matters for reading the quarterly update one small Texas developer released this morning.

New Era Energy & Digital, Inc. (NASDAQ: NUAI), based in Midland, Texas, is building a campus called Texas Critical Data Centers. It sits on a 493-acre site in the Permian Basin, and the company expects its capacity to scale to 1.4 GW over time. For now, it earns very little revenue, so its value rests on whether the project gets built and leased. 

The most important piece is already in place. On September 21st, the company signed a 20-year power purchase agreement with Luminant ET Services Company LLC, an affiliate of Vistra Corp. (NYSE: VST). The deal covers a minimum of 200 MW and up to 207 MW for Phase 1. The power comes from Vistra’s 1,180 MW natural gas plant in Odessa, which sits right next to the site. Power is expected in the third quarter of 2027, with initial ready-for-service targeted for the fourth quarter of that year.

The new update moves attention to the next question, which is who will rent the space. New Era says it is in advanced negotiations on the Phase 1 lease documents under a non-binding letter of intent covering Phases 1 and 2 with the same prospective tenant. The tenant has not been named. Chief Executive Charlie Nelson said “our focus is on our advanced negotiations for the Phase 1 lease.” A non-binding letter shows serious interest, but it is not a contract, and either side can still walk away. 

Phase 2 is a bigger undertaking. Plans call for roughly 550 MW of new behind-the-meter generation with Thunderhead Energy Solutions, and the air permit application has been filed. Behind-the-meter means the power is produced on site rather than drawn from the grid

That permit application runs into a statewide issue. On September 21st, the same day the Vistra deal was announced, Texas Governor Greg Abbott directed the Texas Commission on Environmental Quality to halt permits sought by data center projects until the state’s grid operator, ERCOT, completes a statewide audit. The audit covers both grid reliability and water use. ERCOT expects to finish around December 10th. New Era’s release does not address the pause. In September, the company said it already had construction permits in hand for Phase 1.

The balance sheet tells its own story. At October 31st, New Era reported $187M in total cash, but only $49M was unrestricted. Of the rest, $118M is posted as cash collateral supporting a letter of credit for the power agreement. A $64M private placement went toward repaying borrowings from the company’s Macquarie facility. Debt stood at $20M. That debt was cash collateralized. The company keeps an option for up to $200M of Macquarie financing, available only after a lease is signed, plus about $175M of remaining capacity under its at-the-market program and shelf registration.

That fundraising has come at a cost to existing shareholders. The company reported about 56.8 million shares outstanding on March 9th and about 106.6 million by August 10th, before the October placement added more. Each new share sold shrinks the slice of the company that every existing share represents. 

What emerges is a project that has solved its supply problem but not its demand problem. A signed lease would unlock the post-lease financing and give the campus a revenue stream. Without one, the company carries committed power and tied-up collateral with a modest amount of free cash. Stocks at this stage swing sharply on news, as this one did when it jumped about 30% the day the Vistra agreement became public. A named tenant, or the end of the Texas permit pause, will say more about where this project is headed than anything in this quarter’s numbers.