Rio2 – Q3 Update; Production Still Suffering from Weather, Q4 Recovery Expected

To View the Complete Report

Author: Atrium Research September 28, 2026

Ben Pirie| Equity Research Analyst | [email protected] | 647-688-9661

Nicholas Cortellucci, CFA | Equity Research Analyst | [email protected] | 647-391-3314

PLEASE REVIEW THE DISCLOSURES AT THE BOTTOM OF THE PAGE

What you need to know:

  • RIO provided a Q3 operations update at Fenix, where two major winter storms and three additional single-day snowfall events, driven by a super El Niño, halted mining for extended periods during the quarter.

  • Based on the monthly figures provided, we estimate Q3 production of ~8.8Koz (roughly flat QoQ), with the Company projecting ~17.0Koz in Q4. Commercial production remains on track for Q4.

  • RIO also started surface drilling at Condestable, outlined six new district targets, and was added to the MVIS Global Junior Gold Miners Index.

This morning, Rio2 (RIO:TSX, RIOFF:OTC) provided an operations update on its Fenix Gold Mine in Chile, outlining the impact of the series of severe winter storms during Q3. Based on the monthly production figures in today’s update (actual through July, projected for August and September), we estimate Fenix produced ~8.8Koz of gold in Q3 (roughly flat QoQ), and the Company is projecting ~17.0Koz of gold in Q4. As such, we have lowered our Fenix estimates to reflect the update (Q3/26E 8.8Koz and Q4/26E 17.0Koz, prev. 17.9Koz and 23.7Koz), while the Company continues to target commercial production in Q4. In addition, over the past two weeks, RIO released a company-wide exploration update across Condestable, Fenix, and Kalzas, and was added to the MVIS Global Junior Gold Miners Index. We are maintaining our BUY rating and target price of C$5.75/share on Rio2.

Fenix, which is in the ramp-up stage of its first year of production, experienced two major winter storms during the quarter (which was previously disclosed to investors), characterized by heavy snowfall and high winds. The first storm (July 17ᵗʰ to 24ᵗʰ) forced a full suspension of mining activities, with personnel evacuated from site and no material moved for roughly a week, followed by several days of reduced ore placement as the site recovered. The second storm (August 10ᵗʰ to 22ⁿᵈ) was more severe, halting mining entirely for ~11 days, with ore stacking not resuming until the 24ᵗʰ. Following the August storm, the site also experienced three additional significant single-day snowfall events (see page 2 below for a visual of the impact). During these events, operations were safely suspended and personnel evacuated, while the leach pad, process plant, and power generation facilities continued operating at reduced capacity.

Encouragingly, the data shows that when uninterrupted, Fenix is capable of performing at the targeted rate. On days without weather disruptions, total tonnes moved regularly reached 30-40Kt, and ore placed on the pad frequently approached or exceeded the targeted 20Ktpd (see Figure 2 below). Looking ahead, the Company noted that weather conditions have begun to improve gradually, although long-range forecasts indicate that unseasonal snowfall may continue through December. Site management is implementing several initiatives to recover production losses, and assuming minimal weather disruptions, the Company is projecting production of ~4.0Koz, ~6.0Koz, and ~7.0Koz in October, November, and December, respectively (~17.0Koz in Q4). This implies 2026 production of ~40Koz, below the original 60-65Koz guidance that was withdrawn in August.

Our Take The impact from the winter storms was larger than we initially anticipated. However, it does not appear to point to any underlying operational issues at Fenix, with production rates on days without weather disruptions demonstrating that the operation can reach targeted throughput as the ramp-up continues. We also view RIO’s disclosure around the weather impacts on production and updating Q4 projections as a positive. Notably, December’s projected production of 7.0Koz represents an annualized run rate of 84Koz, approaching production rates we expect in 2027.

To view the complete report, click on the button above.

Related posts

Subscribe to Newsletter

Subscribe VBNG Newsletter for news. Let's stay updated!