The Rising Price of Building America’s Lithium Supply

Big construction projects rarely finish at the price first written on paper, and a lithium mine taking shape in the Nevada desert has just proven the point. Today, Lithium Americas Corp. (NYSE: LAC, TSX: LAC) said its definitive estimate for building the first phase of its Thacker Pass project now stands at $3.83B. The previous figure, used since early 2024, was $2.93B. That is an increase of about $900M, or roughly 31%. 

Thacker Pass sits in Humboldt County, Nevada. The company describes it as America’s largest integrated source of battery-grade lithium carbonate, the white powder that ends up inside electric vehicle batteries. Phase 1 is designed to produce 40,000 tonnes a year. The lithium is locked in clay, and no one has yet extracted lithium from clay at commercial scale, which is one reason the project draws so much attention. Lithium Americas owns the project through a joint venture with General Motors Company (NYSE: GM), which invested $625M in 2024 for a 38% stake and the right to buy Phase 1 output for 20 years.

Most of the extra cost comes back to people. Higher installation rates for piping, steel and equipment added $245M. Wage inflation for craft workers added $150M, and higher pay for engineering and construction management staff added another $150M. More of those staff added $100M. The company also set aside $150M in extra contingency, and tariffs and logistics contributed about $100M. 

The schedule, at least, has not moved. Mechanical completion, the point where the plant is built and ready for testing, is still targeted for late 2027, with ramp-up through 2028. About 1,900 people are working on site, more than 1,600 of them in the trades, and that number is expected to reach roughly 2,200 by year end. The site has logged 4.7 million work hours without a lost-time incident, and the first crystallizer, a key piece of processing equipment, has arrived. 

So who pays? The company puts the added funding need at about $995M. Lithium Americas plans to put $650M into the joint venture, and up to $315M can be drawn as needed from reserve accounts tied to its U.S. Department of Energy loan. An amendment to that loan, signed yesterday, also cuts a required reserve by about $30M. The company held about $1.3B in cash and restricted cash as of September 30th, and on August 13th it sold $150M of convertible debentures to an affiliate of Yorkville Advisors. Because Lithium Americas is contributing more money, its share of the joint venture will rise, with details still being worked out with the Department of Energy and GM. 

For a company valued at roughly $687M, an overrun of $900M is larger than the whole business is worth on the stock market. Management says the project remains funded, and the cash already raised supports that claim. Still, convertible debentures can turn into new shares later, and loan reserves used now are no longer there as a cushion if costs rise again. Returns matter too. A January 2025 technical report estimated an after-tax internal rate of return near 20%, built on the old $2.93B cost and a lithium carbonate price of $24,000 a tonne. A 31% higher bill lowers that figure unless prices or output make up the difference. 

The case for pushing ahead rests partly on national security. The U.S. produces less than 5,000 tonnes of lithium a year, all from a single Nevada facility, while most global supply comes from Australia, Chile and China. Washington has backed Thacker Pass with a $2.26B loan, and a 2025 restructuring gave the government a 5% stake in Lithium Americas through warrants. Strategic value can attract support, but it does not lower the price of steel, labor or shipping. 

The next year will show whether this estimate holds. Key signs include power reaching the site, the workforce peaking without new delays, and equipment such as the crystallizer moving from delivery to installation. If the late 2027 target stays intact and the cost line stops climbing, today’s update may be remembered as a reset. If not, shareholders could be asked for more.